Infrastructure Project

Brent Cross Thameslink is a collection of four projects:

•Brent Cross West Station – New Train Station to serve the new housing development

•Sidings & Rail Systems – Enabling project of rail changes to allow construction of the station

•TOC Accommodation & Fuel Farm – Enabling project to allow for relocation of sidings to allow construction of the station

•Waste Transfer Station including Highways – Enabling project to allow for relocation of existing waste transfer station which will allow for the commencement of the housing scheme.

At a glance

  • 1 programme
  • 4 projects
  • 17 stakeholders/ suppliers
  • £419 Million
  • 2020 – station delivery date

Problem Statement

Historical performance of similar programmes meant an 30% cost overrun was anticipated in Brent Cross. Public funding is linked to predictable programme performance and cost overruns could not occur. Aspen Global was engaged to assist the project team to implement collaborative working processes to deliver the project on time and in budget

Our Brief

To install a collaborative planning and control process across the programme to aid programme predictability and engage the strategic supply chain.

Our Approach 

Facilitated collaborative sessions to establish ‘Best’ Target programmes across projects workstreams.

Established governance structure with escalation process

Implemented and supported collaborative 8 & 3 week detailed look ahead sessions focused on delivery of construction plan

Facilitated sessions visualizing key risks from core supporting processes incl design and planning permissions with action plans to mitigate.

Full process ownership transferred to project team for sustainability of approach.

Benefits

Initial direct savings of £200K in prevented delays

Programme predictability improved 20% ( PPC Metric )

Identified 50 Core activities not listed in P6 programme added to cost loaded programme

 

Diagnose & Envision

Lead & Improve

Verify , Embed & Repeat

Business Diagnostic Collaborative planning ROI Analysis
Visual Management Short Term production control Process standardisation
Data Collection 8 Wastes and Challenge DRAMPP Readiness

( Design , Resource , Access , Materials Plant & Permissions )

Our Clients
Ashgal
Balfour Beatty
Capita
Caterpillar
Costain
Cross Rail
Currie & Brown
Hampshire County Council
Iveco
Network Rail
Newholland Construction
Owens Corning
Oxford City Council
Premier Inn
RAF
Severn Trent Water
Skanska
Speller metcalfe
Vauxhall